New Ag Building

It’s been a slow process but we’re starting to finally move forward again with the erection of our new Ag building..

Sept 2013 saw the rock and the extension of our existing pad..

Sept 2013 - Pad inprovement Sept 2013 - Pad inprovement

January 2014 our old shallow well finally went dead so in goes the new well with submersible pump. The well is capable of about 50 gpm.

Jan 2014 - New well

Moving forward to Aug 2014 and the foundation is dug out.. Wild turkeys enjoying the new territory…

 IMG_20140830_131309IMG_20140830_131420

Early Sept 2014, we’re ready to pour the cement slab and add stem walls.

Sept 2014 - Ready to pour slab